    - PCMC COST RM34M HIGHER THAN ORIGINAL PLAN


    KUALA LUMPUR: The RM391 million building cost of the Prince Court Medical Centre (PCMC) was RM34 million higher than the original contract awarded to Peremba Construction Sdn Bhd, said Datuk Seri Abdullah Ahmad Badawi yesterday.

    The prime minister said the original contract valued at RM 357 million was given to Peremba through an open tender in September 2002.

    "Under the contract, Peremba was required to complete the building of PCMC in 30 months or not later than April 2005," he said in a written reply to Hee Lay Sian (Petaling Jaya Selatan-PKR) in Dewan Rakyat.

    Abdullah said the company, however, was unable to complete the project within the agreed period and had asked to be given additional time.

    "PCMC had agreed to give the additional six months until October 2005," he said.

    Nevertheless, he said the contract with Peremba was terminated in October 2006 when it was still unable to complete the works despite the extension.

    Abdullah said in December 2006, PCMC appointed Sunway Construction Sdn Bhd to replace Peremba to complete the unfinished works.

    "Sunway was chosen because it has a good work performance record. It was also a contractor in building KLCC Convention Centre which it had completed within the agreed period," he said.

    Following that, Abdullah said Sunway had completed the remaining construction of PCMC in June last year.

    This newspaper cutting is dated 18 November 2008, The Edge Financial Daily.